Handling and storage
AS profiles are delivered to site in packs. Packer sheets are used at the bottom of the packs to provide protection and the ends of the packs are wrapped with plastic. Maximum pack weight is 2 tonne.
The packs can be off-loaded directly to the roof, or to a storage area, which should be dry and well away from traffic. Packs may be stacked using suitable wooden bearers and packers. Bearers should be placed above each other.
Handle AS profiles carefully to avoid marking weather sheets or liners. Lift sheets from the pack - do not drag them. Observe site health and safety procedures and the results of manual handling and other assessments.
Preparation Before fixing any sheets check the squareness and accuracy of the steelwork. Determine the direction of the prevailing wind. Check sheets for damage before fixing.
Installation
Roofs - general sequence
Observe the general installation sequence: - Lay and fix weather sheet (see laying sequences for sheets below).
- Fix flashings. Use foam filler pieces and butyl sealant to form weather tight junctions.
|